# 📖 Risk Register

[Embedded content](https://www.youtube.com/embed/YvsoTZkPdPU)

**This screen allows you to:**

-   Define risk events
-   Define mitigated values for risk events 

![](https://cdn-assets.productfruits.com/fa5a7db8-4fc8-45dc-97ce-36691745a917)

###   
**How to Define a Risk Event** 

The following fields are available when defining a risk event:

-   **Code**: A short, unique identifier for the risk event, used to reference it on other pages such as Risk and Risk Drivers. 
-   **Name**: A descriptive label for the risk event, used to identify it clearly when viewing or reporting on the register.
-   **Category:** Classify the risk event as either a Threat or an Opportunity. Threats are risk events with a negative impact on the project if they occur (i.e delays), while Opportunities are risk events with a positive impact if they occur (i.e. time saving). Note that Impact is always entered as a positive number — Category alone determines the direction the impact is applied in, not the sign of the value you enter.
-   **Probability Distribution**: We offer two types
    -   Single value, e.g, 50%
    -   Uniform
-   **Probability%**: The probability value.
-   **Impact Distribution**: We offer 4 types
    -   Single value
    -   Uniform 
    -   Triangle
    -   BetaPERT
-   **Impact**: The Impact value
-   **Description (Optional)**: A description of the event 
-   **Notes (Optional)**: A field that can be used to keep notes about the risk event
-   **Reoccurrence(Optional)**:  The reoccurrence setting controls how many times a risk can occur during a single iteration for each activity it is assigned to. For example, if the recurrence is set to 1 and the risk event is assigned to Activity A and Activity B, the risk can occur up to once on Activity A and up to once on Activity B within the same iteration. If the recurrence is increased to 2, the risk can occur up to twice per iteration for each assigned activity.
-   **Independent (Optional):** This field can be activated by clicking the plus (+) button.
    -   An independent risk event can have different impact values within its impact range for different activities.
    -   A dependent risk event has a fixed impact value from its impact range that applies equally to all affected activities.
    -   By default, if this field is not activated, all risk events are considered independent.

### **How to add Mitigated Values**

To define mitigated values for your risk events, click the Mitigation button at the top of the table. This will show additional fields for all risk events.

 ![](https://cdn-assets.productfruits.com/c5ead13d-ef8a-4dae-b236-cc201fd738bf)

When the mitigation section is activated for the first time, the fields are automatically filled with the same values as the original (pre-mitigation) ones. You can then adjust them to show the reduced probability and/or impact after mitigation actions are applied.

Mitigated fields include:

-   **Mitigated Probability Distribution**: The probability distribution type after mitigation
-   **Mitigated Probability (%)**: The likelihood of the risk occurring after mitigation.
-   **Mitigated Impact Distribution**: The impact distribution type after mitigation.

### **Run Risk Analysis with Mitigation**

Once the Mitigation section is set up, you can go to the main [Risk screen](https://help.nodeslinks.com/en/article/-risk) to assign risk events to activities (if not assigned already) and run the analysis.

When you click the Run button:

-   If mitigation values are set up, a pop-up will appear asking you to choose between:
    -   Run with mitigation: runs two scenarios (with and without mitigation) and shows both results on the same chart.
    -   Run without mitigation: runs only the scenario using the original (pre-mitigation) values.  
         

![](https://cdn-assets.productfruits.com/07e4ceff-8d06-4d2b-9481-f2d6b6348aec)

N.B. *The mitigation section is filled by default with the pre-mitigation values. If these values are not changed, clicking Run will automatically run a single scenario using the pre-mitigation values, and the option to choose between running with or without mitigation will not appear.*