# Timeline

## Introduction

The **Timeline** page within the Portfolio feature provides a visual Gantt-style chart that displays how each **Portfolio**, **Program**, and **Project** spans across time.  
It enables users to quickly assess project timelines, spot scheduling patterns, and identify alignment or deviations across their portfolio.

This article will guide you through:

-   Understanding the Timeline visualization
-   Using different timeline views
-   Accessing detailed project dates

![](https://cdn-assets.productfruits.com/148263ce-7a00-4100-acf8-445070d836af)

## Timeline Overview

The Timeline shows two sets of bars for each row:

-   **Baseline Schedule** (yellow line)
-   **Current Schedule** (blue line)

This dual-bar setup allows users to easily compare how the original plan and the latest project updates align or diverge over time.

Each row represents a project, and projects are grouped under their respective portfolios or programs for easier navigation.

By hovering on any project row, you can quickly see:

-   **Baseline Start Dates, End Dates and duration**
-   **Current Start Dates, End Dates and duration**

This provides precise scheduling information without needing to dive into individual project reports.

![](https://cdn-assets.productfruits.com/a619d85e-25b6-465e-b43a-5da131d4b561)

## Navigating the Timeline

At the bottom right of the screen, you can adjust your view:

-   **Months View**: Displays projects at a monthly level of detail.
-   **Quarters View**: Displays projects grouped by quarters.
-   **Years View**: Displays a more condensed view over multiple years.
-   **Fit to Screen**: Automatically adjusts the zoom to fit all visible data.

If you are in a very detailed (granular) view — such as **Months View** — and wish to quickly reorient to the current date, click the **Today** button.

![](https://cdn-assets.productfruits.com/aca8d117-8baf-4fcd-83cf-c858af1c49b0)