Release 128 – Calculate Critical Path Your Way

This release gives you more flexibility in how you calculate critical path, makes it easier to explain schedule changes, and modernizes one of the most-used screens in the platform.

What’s New in Release 128?
 

1. Calculate Critical Path Your Way

You can now choose between Longest Path and Total Float for critical path calculation.

Different teams prefer different methods. Now you’re in control. As an admin, go to Admin → Projects → Configuration and select the option that fits your project approach.

  • Flexibility to match your methodology
  • Avoid blockers caused by a single calculation method
  • Apply your choice across all projects

2.  Clearer Change Reporting with Gantt

The Change Control Gantt chart has been redesigned to visually match the Timeline view.

  • Compare baseline vs current schedules at a glance
  • Communicate changes simply with clear visuals
  • Maintain consistency across your reporting tools

3.  Modernized Connections Screen

Our Connections screen has been completely refreshed:

  • Simpler design for smoother navigation
  • Spot “linchpins” of your project faster
  • Search and filter capabilities to quickly find connections
  • Network chat preserved to keep your workflows intact

Why These Changes Matter
 

With these updates, you gain:

  • Greater control over how critical path is calculated for your projects
  • Clearer, more visual reporting to communicate changes effortlessly
  • Faster insights into key project connections and dependencies

Together, these improvements help you manage projects with more flexibility, clarity, and confidence.